The Gateway Development Commission (GDC) announced Nov. 18 that the $16 billion Hudson Tunnel Project’s second tunnel boring machine has begun mining the new rail tunnel’s southern tube.
Both tunnel tubes are under construction. The machine building the northern tunnel tube launched in October.
These two machines are building the first 5,100 feet of the new rail tunnel tubes in New Jersey, from the tunnel portal in North Bergen to the Hudson County Access Shaft on the Weehawken-Hoboken border.
When they reach the access shaft, crews will remove the tunnel boring machines and replace them with a second pair designed for the mixed ground conditions under the Hudson River. Including scheduled maintenance pauses, it will take about one year to build this section of the tunnel tubes.
The tunnel boring machines excavate and install the tunnel lining at the same time. Each of these machines will install nearly 850 rings of tunnel lining, assembled from more than 5,000 segments. To date, the machine that launched in October has bored roughly 400 feet of the northern tube and installed more than 60 tunnel lining rings.
Alicia Glen, New York GDC commissioner and co-chair, Balpreet Grewal-Virk, New Jersey GDC commissioner and co-chair, and Tony Coscia, GDC Amtrak commissioner and vice chair said in a joint statement, “The Hudson Tunnel Project is moving forward full steam ahead – we’ve now launched two tunnel boring machines, one for each of the new tunnel’s tubes. We are grateful for the many partners and supporters who have helped us reach this milestone. Every foot that these machines bore brings us closer to delivering the modern, reliable rail system our region needs.”
GDC Chief Executive Officer Tom Prendergast said, “The start of tunnel boring last month was a major milestone for the Hudson Tunnel Project, but it was only the beginning. Launching the second tunnel boring machine marks another significant step toward delivering the most urgent passenger rail infrastructure project in America. We are proud of the hard work that got us to this milestone and committed to bringing the same dedication and grit to the job every day until it is done.”
The Hudson Tunnel Project is separated into 10 construction packages. The first stretch of tunnel boring and construction of the Hudson County Access Shaft is part of the Palisades Tunnel Project. Schiavone Lane Dragados JV is leading construction of this segment, with the Port Authority of New York and New Jersey managing project delivery in partnership with GDC.
The tunnel boring machines cutting through the Palisades are single shield machines designed to efficiently tunnel through hard, dry rock. They each have a 28-foot, 8-inch-diameter cutterhead and trailing gantries that extend roughly 500 feet and weigh more than 1,680 tons.